Nicholas Burdette

Northeast Region Bridge Lead, Vice President , HDR

Nick is a Vice President and the US Northeast Bridge Leader at HDR with over 20 years of bridge design and construction experience. He started his career in the United Kingdom designing two bridges for the 2012 London Olympics.

His technical expertise includes historic bridge rehabilitation, accelerated bridge replacement, and marine foundation design. Nick served as Engineer of Record for the Commercial Street Bridge.

My Sessions at Day 1

Wednesday 10 March 2027

10:20

Sliding into the Future: Accelerated Replacement of the I-376 Commercial Street Bridge

10:20 - 10:40

The I-376 Commercial Street Bridge in Pittsburgh, PA, carries more than 100,000 vehicles daily. To avoid years of traffic impacts from staged construction, PennDOT selected Accelerated Bridge Construction (ABC) for the replacement. A new Arched Steel Delta Frame bridge weighing over 9,000 tonnes was built adjacent to the existing structure on temporary foundations.

During a 17-day interstate closure in July 2026, the existing bridge was removed using conventional and explosive demolition, and the new bridge was slid 37 meters into place, making it one of the heaviest bridge slides ever executed. This presentation highlights the innovative design and construction strategies that made this landmark interstate bridge replacement possible.